Private & Public Sector Building Facilities

Alpha Bank

Project Management for the construction of Alpha Bank’s new office building located at 103, Athinon Ave. in Athens, expanding over a total surface of 19.000 m2. The architectural design was elaborated by A.N. Tombazis Associates & Architects. The construction works started in August, 2006 and were completed within 26 months.

Total surface: 19.000 m2
Starting Date: March 2006
Project Duration: 26 months

Images

Florian S.A.

Project & Construction Management of an office building located in Glyfada

Total surface: 2.500 m2
Starting Date: February 2001
Project Duration: 15 months

ICAP

Project Management for the demolition, structural reinforcement and renovation of an existing office building occupying a total surface of 7.055 m², located at El. Venizelou Str. (Kallithea), on account of ICAP Group A.E.

Τhe building consists of 5 levels and a loft housing a restaurant, as well as 2 underground parking levels. The general contractor was ARRICTON DEVELOPMENT S.A.

The works were initiated on May 2009, and were completed on October 2009.

Images

Interamerican

Project & Construction Management of a “listed” building, located in the center of Athens, Vassilis Sofias Avenue

Total surface: 4.500 m2

Images

Studio Pro

Project & Construction Management for a multi-purpose complex including 4 studios, 1 support area and office facilities, expanding over an area of 8.150 m2. The project employer was DEMCO S.A. and the complex was designed by MRA Architects. The works lasted 5 months, starting from March, 2007.

Total surface: 8.150 m2
Starting Date: March 2007
Project Duration: 5 months

Images

Tsapalos S.A

Project & Construction Management for a 6-level office and commercial use block at 64 Pireos Str. (Moschato) with underground parking , occupying a total area of 15.000 m2 . The project employer was S. Tsapalos S.A. and the architectural design was elaborated by MRA Architects. The works were initiated on January, 2006 and were completed within 8 months.

Total surface: 15.000 m2
Starting Date: January 2006
Project Duration: 8 months

Images